| SUB-BASE
REQUIREMENTS |
| NOTE:
Individual installation sites may vary and the following information
is offered as a general guideline only. For specific requirements,
contact SpectraTurf Phone (800) 875-5788 Fax (909) 734-3630
|
| PART
1 - GENERAL |
| 1.1 |
Preparation: The sub-base of the entire area to be surfaced shall
be cleared of any foreign materials and treated to eliminate growth
of grass, weeds, shrubbery, trees, etc. |
| 1.2 |
The native sub-base shall be graded to allow for proper water drainage
that will prevent sub-base erosion. |
| 1.3 |
The native sub-base shall be compacted to a 90% rating. |
| |
|
| PART
2 - SUB-BASE SURFACE OPTIONS |
| 2.1 |
Asphalt/Concrete: A minimum three (3) inch layer shall be applied
over the sub-base materials to a finished of + 1/8" when measured
with a ten foot straight edge. |
| 2.2 |
The concrete surface shall cure a minimum of thirty (30) days. |
| 2.3 |
Asphalt cure shall be a minimum of seven days. |
| |
|
| PART
3 - CORRECTIONS |
| 3.1 |
Any portion of the above stated work shall be inspected by SpectraTurf,
Inc. prior to application of the safety surfacing materials. |
| 3.2 |
Any corrections deemed necessary by SpectraTurf or the Architect
shall be completed by the parties responsible for the appropriate
portion of the work prior to the installation of the Safety Surfacing
system. |
| 3.3 |
Under no circumstances shall SpectraTurf assume responsibility nor
warranty cost for any failure of work completed by others (see Statement
of Warranty). |